Total
Project Value: |
$ 1.4 Mil |
Period of Performance: |
5 Months |
Client: |
KeySpan Energy Corporation |
Mobilize, excavate and load-out 5,000 cubic yards Coal
Tar residue (BTEX) contaminated soils from a 1200 LF perimeter
trench within the foot print of a planned future power
generation plant construction at a former MGP site. Assess
numerous gas lines and other underground utilities that
crossed laterally through the trench and hot-tap, redirect
or close and cap lines as required. Over 30 personnel working
in Level C Personal protection with 3 backhoes and excavators
were employed on this project. |