Total Project
Value: |
$ 2.8 Mil |
Period of Performance: |
3 Months |
Client: |
CODE Environmental /
Confidential Pharmaceutical Company |
Mobilize, site clearing and the ‘surgical’ excavation
/ load-out of almost 6,000 tons of soils, debris and concrete
removed to six feet depth or bedrock (whichever was encountered
first) from 13 waste zones impacted with multiple types
and levels of contaminants (VOC’s, SVOC’s,
BTEX, PAH’s, PCB’s etc.) requiring off site
transportation and disposal ranging from recycling to incineration
at this 1.5 acre NYDEC regulated superfund site. Restoration
included complete backfill and the installation of a drainage/soils
stabilization fabric and top cover cap of crushed stone.
A total of 10 personnel mainly donning level C Personal protective equipment,
an excavator, 2 Hammers, soil screener, Frac Tank, Dewatering
pumps, Odor Suppression system, dozer, compactor and support
van were deployed to complete this project.
|